We are excited to share that construction of the new Wondersmith Studio and HQ is in progress! Please keep track here and on Instagram.

A 200 year old post and beam barn, on 1.8 acres of green sits near Acton Historic Center, minutes from Route 2 and Concord and 25 minutes to Cambridge. The barn features natural light with a panoramic view of the outdoors, antique heart pine flooring and chestnut beams, and 20’ to the peak of the ceiling. The newly constructed addition features 2 iso spaces, kitchenette, bathroom, and storage/lounge area. The hay loft is being retained - for overdubbing synth solos, or placing room mics... Total space is about 1,150 sq ft, and the design is an open concept tracking/mixing environment. Woodcat Construction is our fantastic design/builder and acoustic oversight is by Matt Azevedo and Acentech. It’s going to be FANTASTIC! Stay tuned!! [Photos chronological bottom to top]

8/15/24: 3 layers of wallboard are in and plastering is finished

8/14/24: custom studio furniture is being designed and constructed

8/1/24: 1st acoustic measurements of the new room

7/28/24: cabinetry, plumbing and electrical fixtures are in hand, ready for installation

7/15/24: 1st layer of wall board complete in barn. Final wallboarding and plastering complete in addition.

4/24/24: Exterior windows and all doors have arrived.

4/19/24: Regrading and excavation to improve drainage around the site complete.

3/1/24: Strapping is installed. Ready for wall board.

2/11/24: Fixtures have been selected: lighting fixtures, door hardware, cabinetry, sinks, toilets, etc.

2/2/23: Closed cell spray foam insulation underway!

12/12/23: Framing rough-in inspection passed

12/10/23: Structural engineer’s recommendations have been executed. Isolation framing complete!

11/17/23: Plumbing rough-in inspection passed

10/24/23: Electrical infrastructure is in, and passed inspection

9/20/23: Plumbing is in! Framing (standard and isolation) near complete.

6/6/23: Ernesto and René of Woodcat are building the addition platform from LVL and engineered wood I-Joists

5/17/23: Concrete spread footings are poured and curing - Framing next week!

4/21/23: Got the Building Permit today! Monday morning Woodcat begins digging holes for the concrete footings. We’re in motion!!

Barn ⇨ Studio